Under Construction

Murfreesboro Road Construction Projects for August 20-26

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: Riverrock Blvd will be reduced to one-lane flagging operation at Beasie Rd for waterline installation work. Road and bridge construction work over Stones River Greenway continues. The greenway trail will be closed around the existing Beasie Rd…

Road Construction

Murfreesboro Road Construction Projects for August 13-19

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: Riverrock Blvd will be reduced to one-lane flagging operation at Beasie Rd for waterline installation work. Road and bridge construction work over Stones River Greenway continues. The greenway trail will be closed around the existing Beasie Rd…

Under Construction

Murfreesboro Road Construction Projects for August 6-12

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction and bridge work over Stones River Greenway. The greenway trail will be closed around the existing Beasie Rd area until further notice due to bridge construction work over the…

Road Construction

Murfreesboro Road Construction Projects for July 23 – 29

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction and bridge work over Stones River Greenway. The greenway trail will be closed around the existing Beasie Rd area until further notice due to bridge construction work over the…

Under Construction

Murfreesboro Road Construction Projects for July 16 – 22

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction and bridge work over Stones River Greenway. The greenway trail will be closed around the existing Beasie Rd area until further notice due to bridge construction work over the…

Road Work Ahead

Murfreesboro Road Construction Projects for July 9 – 15

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction and bridge work over Stones River Greenway. The greenway trail will be closed around the existing Beasie Rd area until further notice due to bridge construction work over the…

Under Construction

Murfreesboro Road Construction Projects for July 2 – 8

Oakland Court Development (Lokey Ave and Academy St) Expected Minor Lane Closures: Monday through Friday: Site construction work continues. Minimal traffic interruptions. Appropriate traffic controls will be in place. Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr) Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction…

Road Construction

Murfreesboro Road Construction Projects for June 25 – July 1

Oakland Court Development (Lokey Ave and Academy St) Expected Minor Lane Closures: Monday through Friday: Site construction work continues. Minimal traffic interruptions. Appropriate traffic controls will be in place. Brinkley Rd Improvement Project (between Blaze Dr and Timber Creek Dr) Expected No Lane Closures: Monday through Friday: Incidental construction work continues. Appropriate traffic controls will…

Road Construction

Murfreesboro Road Construction Projects for June 11-17

Oakland Court Development (Lokey Ave and Academy St) Expected Minor Lane Closures: Monday through Friday: Site construction work continues. Minimal traffic interruptions. Appropriate traffic controls will be in place. Brinkley Rd Improvement Project (between Blaze Dr and Timber Creek Dr) Expected Lane Closures: Monday through Friday: Incidental construction work continues. There will be minor traffic…