Murfreesboro Road Construction Projects for July 4 – 10

Old Pinnacle Building Demolition Work (N Maple St at W College St)

Expected No Lane Closures: Monday through Friday: Site construction work continues. There will be minor traffic interruptions. Appropriate traffic controls will be in place.

Oakland Court Development (Lokey Ave and Academy St)

Expected Road Closures: Monday through Friday: As part of the Oakland Court development, Academy St will be closed to through traffic between Palm Ct and Hembree St. Lokey Ave will also be closed at Academy St. Appropriate traffic controls and detours will be in place.

Warrior Dr Widening Project

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: Pavement marking and sidewalk work continues on Warrior Dr. There will be lane closures and traffic shifts. Appropriate traffic controls will be in place.

Underground Utility Work (Elam Farms Pkwy just north of Joe B Jackson Pkwy)

Expected Lane Closures: Monday through Friday, 8:30 am to 3:30 pm: Comcast crews will be installing underground fiber optics lines along Elam Farms Pkwy. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Turn lane Installation Work (Butler Dr south of the railroad tracks)

Expected Road Closures: Monday through Friday: As part of a private development, the new left turn lane on Butler Dr will be paved and striped. Appropriate traffic controls and detours will be in place.

Annual City Street Paving Projects

Expected Lane Closures: Monday through Friday, 9:00 AM – 3:00 PM: City contractor will be performing construction work at the following streets:
1. Saint Andrews Dr between Cason Trl and Old Fort Pkwy (pavement markings)
2. Cason Trl between Saint Andrews and Cason Ln (pavement markings)
3. Vine St between Maney Ave and Highland Ave (pavement markings)
4. Public Dr, Shelby St, Mi-Tech Dr and Porter St (paving)
Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.

TDOT Resurfacing Projects

RUTHERFORD COUNTY
The resurfacing on I-840 including concrete ramp repair
• Thurs 7/1 thru Wed 7/7 excl. holiday restrictions 7PM-5AM. There will be alternating lane closures for paving and shoulder stone operations.

RUTHERFORD COUNTY
The grading, drainage, construction of two concrete Bulb-Tee beam bridges, signals and paving on SR 266 (Jefferson Pike) from SR 102 to east of I-840
• Thurs 7/1 thru Wed 7/7 excl. holiday restrictions 9AM-3PM. There will be periodic flagging operation alone SR 266 for construction activities.

RUTHERFORD COUNTY
The grading, drainage, construction of bridges, signals and paving on SR 99 from Cason Ln (LM 15.97) to I-24 in Murfreesboro (LM 18.12)
• Now thru Wed 7/14 Continuous Cason Lane will be closed at its intersection with SR 99 for storm drainage installation. A signed detour will be in place.

RUTHERFORD COUNTY I-840 EB & WB
The grading, drainage, construction of two concrete Bulb-Tee beam bridges, signals and paving on SR 266 (Jefferson Pike)
• Thurs 7/1 thru Wed 7/7 excl. holiday restrictions 38′ 28′ A minimum 2′ shoulders will be maintained between edge lines and barrier rail, which will reduce the overall width including shoulders from 38′ to 28′.

RUTHERFORD COUNTY SR 99
The grading, drainage, construction of a concrete bridge, box culvert, utility relocation and paving of SR99 from Cason Lane to West of I-24
• Thurs 7/1 thru Wed 7/7 excl. holiday restrictions 32.5′ 22′ Traffic will be shifted across the new bridge at LM 17.78 in order to build phase 2 of the bridge.

Edit Post

Murfreesboro.com

Welcome to Murfreesboro.com. This site was designed to help foster communication between the residents of Murfreesboro, Tennessee. Whether you're looking for news, events, jobs, etc. you can find it all right here on Murfreesboro.com.

Related Articles

Back to top button