Oakland Court Development (Lokey Ave and Academy St)

Expected Minor Lane Closures: Monday through Friday: Site construction work continues. Minimal traffic interruptions. Appropriate traffic controls will be in place.

Brinkley Rd Improvement Project (between Blaze Dr and Timber Creek Dr)

Expected Lane Closures: Monday through Friday: Incidental construction work continues. There will be minor traffic interruptions Monday and Tuesday at the new bridge ends. Appropriate traffic controls will be in place

Sewer Installation Work (Minerva Dr between Dr Martin Luther King Jr Blvd and Diana St)

Expected Road Closures: Monday through Friday: Contractor for a private development will be installing sewer lines and manholes on Minerva Dr between Dr Martin Luther King Jr Blvd and Diana St. Traffic to and from Minerva Dr will be detoured onto Apollo Dr and S Baird Ln. Appropriate traffic controls and detour signs will be in place.

Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr)

Expected Lane Closures: Monday Through Friday: City contractor has begun the Beasie Rd construction and bridge work over Stones River Greenway. The greenway trail will be closed around the existing Beasie Rd area. There will be no through trail access between the Old Fort Park and Cason Trailhead. Appropriate traffic controls will be in place.

Annual City Street Paving

Expected Lane Closures: Monday through Friday, 9:00 AM – 3:00 PM: City contractor will be performing construction work at the following streets:

  1. Medical Center Pkwy and GreshamPark Dr (traffic signal and paving improvements)
  2. Adjacent to 2300 block of Haven Dr (storm drain installation)
  3. Old Fort Pkwy between I-24 EB off-ramp and John Rice Blvd (shoulder improvements)
  4. Maple St and Chestnut St (curb & gutter and handicap ramp work)

Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.

TDOT Resurfacing Projects
(Source: TDOT)

NOTE: All lane closures listed below are reflective of necessary adjustments due to the CMA Fest this weekend and the beginning of Bonnaroo next week.

DAVIDSON / RUTHERFORD COUNTIES I-24

The installation of Smartway Intelligent Transportation System (ITS) on I-24 from I-440 to US-231

  • 6/12 – 6/14, 8 P.M. – 5 A.M., There will be alternating lane closures EB and WB for guardrail installation.

RUTHERFORD COUNTY I-24

On-Call Pavement Testing

  • 8 p.m. – 5 a.m., There will be Left and HOV Lane Closures for pavement testing (MM 78 – 82)

The resurfacing on I-24 from E of Epps Mill Road through Bedford County to the Coffee County Line.

  • Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures EB and WB for milling and paving activities Thurs. – Mon. and WB only on Tues. and Wed. (MM 90-97)

RUTHERFORD COUNTY I-840

The resurfacing of I-840 from West Fork Stones River Bridge to near SR-266

  • Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures on I-840 for milling and paving operations. One lane will remain open at all times.

The on-call concrete pavement repair at various locations on various Interstate and State Routes

  • 6/11 at 8 p.m. continuously until 6/14 at 12 p.m., There will be a partial ramp closure at I-840 EB to SR 1 NB, bottom of ramp, to repair/replace damaged concrete. Ramp will remain open.

RUTHERFORD COUNTY SR 99

The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)

  • Continuous, Bridge Avenue will be closed for utility relocation. A signed detour will be in place.
  • 6/11 – 6/14, 8 p.m. – 5 a.m., There will be nighttime flagging operations for open cut installation of utility casing.

RUTHERFORD COUNTY SR 266

The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).

  • Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.

RUTHERFORD COUNTY I-840

Pothole patching via milling and paving

  • Daily, 9 a.m. – 3 p.m., There will be a lane closure of Lane 2 on I-840 WB near the Wilson County line for milling and paving operations. Lane 1 will remain open at all times. (MM 64-65)