Medical Center Parkway Phase II widening requires tree removal and replacement
Improvements increasing capacity and traffic flow from Thompson Lane to the Fountains at Gateway

Landscaped trees will be removed and later replaced along Medical Center Parkway between The Fountains at Gateway and Thompson Lane as the City of Murfreesboro widens the road. The Murfreesboro City Council voted on August 21, 2025, to authorize construction of Phase II, and WGNS Radio reported on September 24, 2025, that construction began that month and is expected to finish by early 2027.
Phase II requires tree removal so crews can add turn lanes and widen the roadway with additional lanes, beginning at Thompson Lane. When the widening is finished, landscaping will be added to the median. Public Infrastructure Executive Director Chris Griffith said the tree removal is a necessary part of the project. “Landscaping has been an important aspect of the overall aesthetic of Medical Center Parkway” said Griffith. “As Phase II widens Medical Center Parkway to increase traffic flow, removing the landscaped trees is a necessary part of this project. However, we want residents and motorists to know that appropriate landscaping will be planted as part of the overall widening project.”
The project will increase capacity on the corridor and improve traffic flow, which the city says is needed to ease congestion on a heavily developed roadway with growing commercial and office development. Phase II adds an additional through lane in each direction, along with turn lanes and traffic signal modifications, from Thompson Lane to The Fountains at Gateway. WGNS reported that the road will be widened to six lanes, with a redesigned median and updated traffic signals.
The work is part of a 3.41-mile widening built in phases to limit disruption to traffic in the corridor. Phase I ran from the I-24 interchange to Thompson Lane. A Rutherford Source article from March 2025 reported that Phase I lanes near the interstate were set to open that month, with final paving possibly completed later as part of Phase II. Phase III will extend the widening from The Fountains at Gateway to NW Broad Street.
City engineers are using the same annual contracts for Phase II that they used for Phase I. The joint group of contractors widening Medical Center Parkway in Phase II is Rollins Excavating, Hawkins Asphalt, S&W Contracting, and Pope Striping. The City contracted Energy Land and Infrastructure, LLC for the professional services contract to design the project. The city is funding the $6.4 million estimated cost of construction through its FY21 and FY22 Capital Improvement Plan budgets.
Drivers should expect lane changes and signal work through the Phase II corridor until construction ends. Neither WGNS Radio nor the Rutherford Source gave a completion date beyond early 2027, and the Rutherford Source article did not mention tree work at all. The city has said the replacement landscaping will be planted as part of the overall widening project.




